5/4/2022 -
Nexans has been awarded a contract worth around €100m by French grid operator RTE to supply and install cables for the 496 MW Le Treport offshore wind farm.
A press release said that the contract comprises 47 km of offshore and 18 km of onshore export cable for the wind farm, which is located more than 15.5 km from Le Tréport and 17 km from Dieppe.
The consortium Eoliennes en Mer Dieppe Le Treport is developing the offshore wind farm. RTE has been appointed by the French government to connect the wind farm from the offshore substation to the onshore power grid by installing two subsea and onshore links.
For the subsea section, Nexans will supply two 23.5 km lengths of 225 kV three-core cable. The cable has hybrid armoring and incorporates a fiber-optic element to remotely monitor the health of the link and transmit information between the offshore wind farm and the onshore base.
Nexans’ Halden plant in Norway will manufacture the subsea cables, while the land cables will come from the Nexans plant in Charleroi, Belgium. The fiber-optic elements will be supplied from the Norwegian site in Rognan. The installation of the subsea cables should start in the second half of 2024.
The cables will be laid by the CS Skagerrak, one of Nexans’ two cable laying vessels. The onshore link will have 18 km of 225 kV single-core cable, similar to that supplied to RTE by Nexans under the current framework contract for onshore cables. Nexans will also be in charge of the cable burial and protection for the onshore section.